  • R403.1

    General

    • Exterior walls sit on continuous concrete, solid or grouted masonry, crushed stone or wood footings bearing on undisturbed soil or engineered fill.
    • Concrete footing size comes from the tables by roof load, stories, foundation type, wall type and soil bearing value; widths may be interpolated between soil values but not extrapolated.
    • Add 2 in of width and 1 in of depth for every 4 ft the building is wider than 32 ft; narrower buildings may take the same off, down to 12 x 6 in.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.1

    Minimum Size

    • Concrete footings are at least 12 in wide and 6 in thick, and project at least 2 in past the wall but no more than their thickness.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.2

    Continuous Footing in Seismic Design Categories D

    • In SDC D, exterior walls always sit on continuous concrete or grouted masonry footings; interior braced panels need them on larger or taller buildings.
    • Where interior bracing footings are needed, they may be spaced up to 50 ft apart if cripple walls are 4 ft or less, panels sit on doubled joists or beams, and bracing lines are no more than twice the building width apart.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.6

    Foundation Anchorage

    • Sill plates and exterior sole plates on slabs are anchored with 1/2 in bolts at 6 ft or less, embedded 7 in, in the middle third of the plate, with a nut and washer.
    • Each plate piece gets at least two bolts, with one within 12 in of each end but no closer than seven bolt diameters.
    • Short offset walls between braced panels need one bolt if 24 in or shorter, and none if 12 in or shorter, when tied to the panels at the corners.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.7

    Footings on or Adjacent to Slopes

    • Buildings on or near slopes steeper than 1:3 follow the slope clearance and setback rules.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.8

    Foundations on Expansive Soils

    Used in checks
    • Foundations and slabs on expansive soil are designed per IBC 1808.6, unless a system with a good local track record is approved.

    Local review: Expansive clay is common around San Antonio; expect an engineered foundation.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.3.1

    Concrete Stem Walls With Concrete Footings

    • In SDC D, a concrete stem wall on a separate footing gets No. 4 hooked dowels at 4 ft or less extending 14 in up, plus No. 4 bars near the top and bottom.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.3.2

    Masonry Stem Walls With Concrete Footings

    • Masonry stem walls in SDC D get the same dowels and bars, and are solidly grouted.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.3.3

    Slabs-on-Ground With Turned-Down Footings

    • In SDC D, monolithic turned-down slab edges get a No. 4 top and bottom, or a No. 5 or two No. 4s mid-depth; separate slabs get No. 3 hooked dowels at 4 ft or less.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.3.4

    Interior Bearing and

    • In SDC D, interior footings under bearing or braced walls that are cast with the slab go at least 12 in below the top of the slab.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.3.5

    Reinforcement

    • Footing rebar is Grade 40 or better, tied in place, with 3 in of cover against earth, 1-1/2 in (No. 5 and smaller) or 2 in in formed exposed concrete, and 3/4 in otherwise.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.3.6

    Isolated Concrete Footings

    • Detached homes of three stories or less with stud bearing walls may use plain isolated footings under columns and piers.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.4.1

    Frost Protection

    • Foundations are protected from frost by going below the local frost line, a frost-protected shallow foundation, ASCE 32, or bearing on rock; never on seasonally frozen soil.
    • Frost protection isn't needed for detached light-frame sheds up to 600 sq ft, or other sheds up to 400 sq ft, with eaves of 10 ft or less.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.6.1

    Foundation Anchorage in Seismic Design Categories C, D

    • In SDC D (and townhouses in C), braced wall lines get plate washers, interior braced and bearing plates get bolts at 6 ft and within 12 in of ends, and buildings over two stories space bolts at 4 ft.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.7.1

    Building Clearances From Ascending Slopes

    • Keep buildings back from the toe of an uphill slope per Figure R403.1.7.1; for slopes steeper than 1:1, the toe is taken where a 45-degree line meets the foundation top.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.7.2

    Footing Setback From Descending Slope Surfaces

    • Footings near a downhill slope are set back per Figure R403.1.7.1; for slopes steeper than 1:1 measure from a 45-degree plane up from the toe.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.7.3

    Foundation Elevation

    • On graded sites the top of the foundation is at least 12 in plus 2% above the street gutter or drain inlet.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.7.4

    Alternate Setbacks and Clearances

    • The building official may approve other setbacks and can require an engineer's slope study.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.8.1

    Expansive Soils Classifications

    • Soil is expansive if its PI is 15 or more and over 10% passes a No. 200 sieve and over 10% is finer than 5 microns, or if its expansion index exceeds 20.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R403.1.3.5.4

    Lap Splices

    • Lap splices follow Table R608.5.4(1); non-contact bars at a splice are no farther apart than a fifth of the lap or 6 in.

    International Residential Code, 2024 · Chapter 4, FoundationsRead the full text (opens UpCodes in a new tab)

  • R506.1

    General

    • Slab-on-ground floors are at least 3-1/2 in thick, designed here or to ACI 332, with concrete strength per R402.2; expansive soil sites follow R403.1.8.

    International Residential Code, 2024 · Chapter 5, FloorsRead the full text (opens UpCodes in a new tab)

Searches all 4,276 IRC 2024 sections, 5,532 IBC 2024 sections and defined terms (Chapters 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33 so far) and each city's local rules as they are added. Section numbers and titles from the International Residential Code and International Building Code, 2024 editions, copyrighted by the International Code Council; the IRC's electrical chapters (34 to 43) follow NFPA 70, the National Electrical Code. Requirements are summarized in our words (IRC Chapters 3 to 43, IBC Chapters 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33); read the full text at the link on each result. Local values come from each city's published documents.

Check your plans against these codes

Start an application and get every flag with its section and fix.

Start an application