Detached houses, duplexes and townhouses up to 3 stories with their own exits use the IRC; every other building uses the IBC (IBC 101.2).

23 sections matching “IBC 105” for San Antonio, TX, the 2024 IRC

  • IBC 105.1

    Required

    • A permit is needed before building, enlarging, altering, repairing, moving, demolishing or changing occupancy, or installing electrical, gas, mechanical or plumbing systems.

    Local review: Cities usually replace Chapter 1 with their own administrative rules. In San Antonio, permits, fees, time limits and inspections follow the city's adopted amendments and DSD procedures; confirm there before relying on these.

    Works withIBC 105.2

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 105.2

    Work exempt from permit

    • No building permit for sheds up to 120 sq ft, fences up to 7 ft (not pool barriers), retaining walls up to 4 ft, walks and drives up to 30 in, finish work and similar; exempt work still has to meet the code.

    Local review: Cities usually replace Chapter 1 with their own administrative rules. In San Antonio, permits, fees, time limits and inspections follow the city's adopted amendments and DSD procedures; confirm there before relying on these. Houses under the IRC have their own exemption list (IRC R105.2), with a larger shed limit.

    Works withIRC R105.2

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 105.3

    Application for permit

    • Applications describe the work, the land (legal description or address), the use and occupancy, the valuation, and include the construction documents, signed by the applicant.

    Works withIBC 107IBC 109.3

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 105.4

    Validity of permit

    • A permit never approves a violation, and the official may still require corrections to the documents.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 105.5

    Expiration

    • A permit expires if work doesn't start within 180 days or stops for 180 days; written extensions up to 180 days each.

    Local review: Cities usually replace Chapter 1 with their own administrative rules. In San Antonio, permits, fees, time limits and inspections follow the city's adopted amendments and DSD procedures; confirm there before relying on these.

    Works withIRC R105.5

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 105.1.1

    Annual permit

    • Facilities with their own tradespeople may get an annual permit for alterations to approved systems.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 105.2.1

    Emergency repairs

    • Emergency replacements may start first, with the application filed the next business day.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 105.2.2

    Public service agencies

    • Utility-owned generation, transmission, distribution and metering equipment needs no permit.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 105.3.1

    Action on application

    • Applications are reviewed in reasonable time; rejections are in writing with reasons.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 105.3.2

    Time limitation of application

    • An application is abandoned after 180 days unless pursued or permitted; extensions of up to 90 days each may be granted in writing.

    Local review: Cities usually replace Chapter 1 with their own administrative rules. In San Antonio, permits, fees, time limits and inspections follow the city's adopted amendments and DSD procedures; confirm there before relying on these.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 202

    Concrete

    • Types by aggregate: carbonate (limestone or dolomite, 40% or less quartz), siliceous (over 40% quartz), lightweight (85 to 115 pcf), sand-lightweight (105 to 120 pcf), and about 30 pcf insulating cellular, perlite and vermiculite concretes.

    Works withIBC 722

    International Building Code, 2024 · Chapter 2, DefinitionsRead the full text (opens UpCodes in a new tab)

  • IBC 716.2.10

    Installation of door assemblies in corridors and smoke barriers

    • Smoke doors installed per NFPA 105.

    International Building Code, 2024 · Chapter 7, Fire and Smoke Protection FeaturesRead the full text (opens UpCodes in a new tab)

  • IBC 710.5.2.2

    Smoke and draft control doors

    • Where required, doors meet UL 1784 at 3.0 cfm/sq ft leakage, installed per NFPA 105.

    International Building Code, 2024 · Chapter 7, Fire and Smoke Protection FeaturesRead the full text (opens UpCodes in a new tab)

Searches all 4,276 IRC 2024 sections, 5,532 IBC 2024 sections and defined terms (Chapters 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33 so far) and each city's local rules as they are added. Section numbers and titles from the International Residential Code and International Building Code, 2024 editions, copyrighted by the International Code Council; the IRC's electrical chapters (34 to 43) follow NFPA 70, the National Electrical Code. Requirements are summarized in our words (IRC Chapters 3 to 43, IBC Chapters 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33); read the full text at the link on each result. Local values come from each city's published documents.

Check your plans against these codes

Start an application and get every flag with its section and fix.

Start an application