Detached houses, duplexes and townhouses up to 3 stories with their own exits use the IRC; every other building uses the IBC (IBC 101.2).

9 sections matching “IBC 714.5” for San Antonio, TX, the 2024 IBC

  • IBC 714.5.1

    Through penetrations

    • Floor penetrations use tested assemblies or listed systems; metal pipes up to 6 in may be sealed or grouted with limits.

    International Building Code, 2024 · Chapter 7, Fire and Smoke Protection FeaturesRead the full text (opens UpCodes in a new tab)

  • IBC 714.5.2

    Membrane penetrations

    • Ceiling membrane penetrations follow 714.5.1; exceptions for metal pipes, small boxes, sprinklers, listed fixtures and double top plates.

    International Building Code, 2024 · Chapter 7, Fire and Smoke Protection FeaturesRead the full text (opens UpCodes in a new tab)

  • IBC 714.5.3

    Dissimilar materials

    • Noncombustible penetrants don't connect to combustibles beyond the firestop unless proven.

    International Building Code, 2024 · Chapter 7, Fire and Smoke Protection FeaturesRead the full text (opens UpCodes in a new tab)

  • IBC 714.5.4

    Penetrations in smoke barriers

    • Smoke barrier firestops have L rating of 5 cfm/sq ft each, 50 cfm per 100 sq ft total.

    International Building Code, 2024 · Chapter 7, Fire and Smoke Protection FeaturesRead the full text (opens UpCodes in a new tab)

  • IBC 714.5.1.2

    Through-penetration firestop system

    • Listed systems with F and T ratings at least 1 hour and the floor's rating; T not needed in wall cavities, at drains, switchgear conduits or small pipes in concrete.

    International Building Code, 2024 · Chapter 7, Fire and Smoke Protection FeaturesRead the full text (opens UpCodes in a new tab)

  • IBC 714.4

    Fire-resistance-rated walls

    • Wall penetrations follow 714.4.1 to 714.4.3; smoke barriers also 714.5.4.

    International Building Code, 2024 · Chapter 7, Fire and Smoke Protection FeaturesRead the full text (opens UpCodes in a new tab)

  • IBC 717.6.1

    Through penetrations

    • Ducts through a rated floor connecting two stories need a floor-line fire damper or 714.5 protection; small steel exhaust ducts through up to three floors in walls are excepted.

    Works withIBC 714.5IBC 712.1.9

    International Building Code, 2024 · Chapter 7, Fire and Smoke Protection FeaturesRead the full text (opens UpCodes in a new tab)

Searches all 4,276 IRC 2024 sections, 5,532 IBC 2024 sections and defined terms (Chapters 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33 so far) and each city's local rules as they are added. Section numbers and titles from the International Residential Code and International Building Code, 2024 editions, copyrighted by the International Code Council; the IRC's electrical chapters (34 to 43) follow NFPA 70, the National Electrical Code. Requirements are summarized in our words (IRC Chapters 3 to 43, IBC Chapters 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33); read the full text at the link on each result. Local values come from each city's published documents.

Check your plans against these codes

Start an application and get every flag with its section and fix.

Start an application