Detached houses, duplexes and townhouses up to 3 stories with their own exits use the IRC; every other building uses the IBC (IBC 101.2).

14 sections matching “IBC 110.3” for San Antonio, TX, the 2024 IRC

  • IBC 110.3

    Required inspections

    • The required inspections are footing and foundation, slab and under-floor, flood elevation, framing, Type IV connections, lath and gypsum, balcony waterproofing, fire penetrations, energy, other, special and final.

    Works withIBC 110.3.1IBC 110.3.12

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 110.3.1

    Footing and foundation inspection

    • After footing excavation with reinforcing (and forms) in place, before concrete; ready-mix needn't be on site.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 110.3.2

    Concrete slab and under-floor inspection

    • After in-slab reinforcing, conduit and piping are in, before concrete or subfloor.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 110.3.4

    Frame inspection

    • After roof sheathing, framing, fireblocking and bracing are in and rough electrical, plumbing and HVAC are approved.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 110.3.5

    Types IV-A, IV-B and IV-C connection protection inspection

    • In mass-timber Types IV-A to IV-C, wood cover protecting connections is inspected before other finishes.

    Works withIBC 2304.10.1

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 110.3.6

    Lath and gypsum panel product inspection

    • After lath and gypsum board are up, before plaster or taping; non-rated, non-shear gypsum is exempt.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 110.3.8

    Fire- and smoke-resistant penetrations

    • Firestopping at joints and penetrations isn't concealed until inspected.

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

  • IBC 110.3.9

    Energy efficiency inspections

    • Energy inspections cover insulation R- and U-values, window U-values, duct insulation and HVAC and water-heating efficiency.

    Works withIBC Chapter 13

    International Building Code, 2024 · Chapter 1, Scope and AdministrationRead the full text (opens UpCodes in a new tab)

Searches all 4,276 IRC 2024 sections, 5,532 IBC 2024 sections and defined terms (Chapters 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33 so far) and each city's local rules as they are added. Section numbers and titles from the International Residential Code and International Building Code, 2024 editions, copyrighted by the International Code Council; the IRC's electrical chapters (34 to 43) follow NFPA 70, the National Electrical Code. Requirements are summarized in our words (IRC Chapters 3 to 43, IBC Chapters 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33); read the full text at the link on each result. Local values come from each city's published documents.

Check your plans against these codes

Start an application and get every flag with its section and fix.